Green Light

It is my pleasure to report today that I’ve received word that the “outhouse upgrade” concept previously discussed has been approved by the municipal authorities, thus crossing an important threshold for this project: all the regulatory issues have been resolved! All that remains is to follow through with the particulars, but the important bit — … Continue reading Green Light

Uranium 1.708

It’s been cold here for the last few days, near freezing, then cool and rainy, so while I do have the power system running, finally, I have not been motivated to get out there and do the water test and finish the tub installation. It’s supposed to warm up a bit later this week and … Continue reading Uranium 1.708

Scary Thing 2/5

Previously, I had mentioned that there were 4 big scary things about this whole project. Actually, there are five. The one I didn’t mention then was the fire place. That thing’s gonna get quite hot 🙂 Today, though, it was finally time to cross of one of those scary things as done: the power system! … Continue reading Scary Thing 2/5

Power Center Woes

Yesterday, the replacement battery modules arrived by freight, in excellent shape and right on time, if by “on time” we mean “they sat for more than a week in the warehouse but once they got moving, they got here promptly, considering they’re heavy freight”. This time I remembered to use my hoist to get them … Continue reading Power Center Woes

Albuqerque?

It seems my replacement batteries are finally on the move from California. Today’s tracking report has them at a depot in Albuquerque. I do hope they don’t take a wrong turn from there. You know, I’ve known about the city of ABQ for many years but never really stopped to think about how to spell … Continue reading Albuqerque?